City Council · November 20, 2018
R-395-2018
Amend Whaley Construction contract for Cedar Lane Sidewalk Project.
A Resolution authorizing the Mayor to amend Contract No. C-18-0125 with Whaley Construction, LLC for the Cedar Lane Sidewalk Project, increasing the contract amount by $36,763.80 for a new contract total of $338,197.80 and extending the date of completion to November 30, 2018.
See this item across every meeting →On November 20, 2018, the City of Knoxville, TN City Council adopted “Amend Whaley Construction contract for Cedar Lane Sidewalk Project.” by a vote of 9–0.
Motion to approve the resolution
Moved by Mark Campen · seconded by Andrew Roberto
Topics: Roads & infrastructure
The vote as recorded
Aye · 9
Public forum
The clerk’s minutes record no speakers at the public forum for this meeting.
A sign-up count from the minutes — not a measure of overall public opinion.
Minutes of the 20 November 2018 meeting — page 13
Share & embed