City Council · October 2, 2012

R-272-2012

Authorize Change Order No. 1 for Site Development Detention Pond Improvement

A Resolution authorizing the Mayor to execute Change Order No. 1 to Contract No. C-12-0218 with Cozy Excavation & Contracting, LLC for the Site Development Detention Pond Improvement Project to increase the contract price by $11,158.85 for a new contract total of $110,275.40, and to extend the date of completion.(Requested by Department of Engineering)

See this item across every meeting →

On October 2, 2012, the City of Knoxville, TN City Council adopted “Authorize Change Order No. 1 for Site Development Detention Pond Improvement” by a vote of 9–0.

Unanimous Adopted 9-0-0-0

APPROVE RESOLUTION NO. R-272-2012

Moved by Duane Grieve · seconded by Nick Della Volpe

Topics: Roads & infrastructure

The vote as recorded

Aye · 9

Nick Pavlis District 1 Duane Grieve District 2 Brenda Palmer District 3 Nick Della Volpe District 4 Mark Campen District 5 Daniel T. Brown District 6 George C. Wallace At-Large Seat A Marshall Stair At-Large Seat B Finbarr Saunders At-Large Seat C

The figures in this motion

  • $11,158.85

  • $110,275.40