R-273-2012

Authorize Change Order No. 1 for 2012 Resurfacing Project

A Resolution authorizing the Mayor to execute Change Order No. 1 to Contract No. C-12-0252 between the City of Knoxville and Rogers Group, Inc., to increase the contract price by $128,669.25 for a new contract total of $7,039,507.25, for the 2012 Resurfacing Project.(Requested by Department of Engineering)

See this item across every meeting →

On October 2, 2012, the City of Knoxville, TN City Council adopted “Authorize Change Order No. 1 for 2012 Resurfacing Project” by a vote of 8–0.

Adopted 8-0-1-0

APPROVE RESOLUTION NO. R-273-2012

Moved by Brenda Palmer · seconded by Nick Della Volpe

Topics: Roads & infrastructure

The vote as recorded

Aye · 8

Nick Pavlis District 1 Duane Grieve District 2 Brenda Palmer District 3 Nick Della Volpe District 4 Mark Campen District 5 Daniel T. Brown District 6 George C. Wallace At-Large Seat A Finbarr Saunders At-Large Seat C

Abstain · 1

Marshall Stair At-Large Seat B

The figures in this motion

  • $128,669.25

  • $7,039,507.25

All spending approved by this body →