Authorize change order for Third Creek Greenway Bridge Replacement Project.
Its full path through the City Council — 1 appearance on record, oldest first. Every step links back to the official minutes.
-
Step 1
July 9, 2013A Resolution authorizing the Mayor to execute Change Order No. 2 to Contract No. C-13-0032 with Design & Construction Services, Inc., for the Third Creek Greenway Bridge Replacement Project, increasing the contract price by $36,199.10 for a new contract total of $232,722.10, and extending the completion date to July 31, 2013.(Requested by Department of Engineering)