City of Knoxville · City Council

R-32-2024

Authorization to amend contract for Kingston Pike Complete Connections Project

Its full path through the City Council — 1 appearance on record, oldest first. Every step links back to the official minutes.

  1. A Resolution authorizing the Mayor to amend the contract with Southern Constructors, Inc. for the Kingston Pike Complete Connections Project, increasing the contract amount by $93,727.36 for a new contract total of $2,293,701.36 and extending the completion date to March 14, 2024.(Requested by Department of Engineering)

    Unanimous Adopted 8-0-0-1

    Passed at this meeting.

    Roll call & discussion →

    Source: official minutes (PDF) for January 23, 2024.