City of Knoxville · City Council
R-40-2020
Authorize Mayor to amend contract with Morgan Contracting for Cured-in-Place Pipe Project
Latest action, January 28, 2020: Adopted 8-0-0-1
1 meeting on record, oldest first.
-
Step 1
January 28, 2020A Resolution authorizing the Mayor to amend Contract No. C-20-0092 with Morgan Contracting Inc. for the Cured-in-Place Pipe Project, increasing the contract amount by $130,158.81 for a new contract total of $950,863.81.(Requested by Department of Engineering)
Moved by Gwen McKenzie · seconded by Lauren Rider
Share this vote →Aye · 8: Charles Thomas, Lynne Fugate, Amelia Parker, Stephanie Welch, Andrew Roberto, Lauren Rider, Gwen McKenzie, Janet Testerman
Absent · 1: Seema Singh
Source: official minutes (PDF) for January 28, 2020, page 12.