Board of Commissioners · December 20, 2021
R-21-12-408
Approve construction contract for South Northshore Greenway Project Phase 1B.
Consideration of a Resolution of the Commission of Knox County, Tennessee, approving a construction contract in the amount of $828,768.50 with Design and Construction Services, Inc. for Phase 1B of the South Northshore Greenway Project
See this item across every meeting →On December 20, 2021, the Knox County, TN Board of Commissioners adopted “Approve construction contract for South Northshore Greenway Project Phase 1B.” by a vote of 11–0.
Part of Northshore Drive
Approve R-21-12-408
Moved by Randy Smith · seconded by Courtney Durrett
Topics: Roads & infrastructure
The vote as recorded
Aye · 11
Public forum
The clerk’s minutes note 1 speaker at the public forum for this meeting.
A sign-up count from the minutes — not a measure of overall public opinion.