Approve construction contract for South Northshore Greenway Project Phase 1B.
Latest action, December 20, 2021: Adopted 11-0-0-0
1 meeting on record, oldest first.
-
Step 1
December 20, 2021Consideration of a Resolution of the Commission of Knox County, Tennessee, approving a construction contract in the amount of $828,768.50 with Design and Construction Services, Inc. for Phase 1B of the South Northshore Greenway Project
Approve R-21-12-408
Moved by Randy Smith · seconded by Courtney Durrett
Share this vote →Aye · 11: Larsen Jay, Courtney Durrett, Terry Hill, Dasha Lundy, Kyle Ward, John Schoonmaker, Richie Beeler, Carson Dailey, Randy Smith, Charles Busler, Justin Biggs