Amend Smith Seckman Reid contract for pipe rehabilitation
Latest action, May 27, 2025: Adopted 8-0-0-1
1 meeting on record, oldest first.
-
Step 1
May 27, 2025A Resolution authorizing the Mayor to amend the contract with Smith Seckman Reid, Inc. to provide professional engineering design services for the Cured-in- Place Pipe Infrastructure Rehabilitation Project, increasing the contract amount by $19,800.00 for a new contract total of $136,080.00 and extending the date of completion to August 31, 2026. (Requested by Engineering Department)
Councilmember Rider moved to approve the resolution
Moved by Lauren Rider · seconded by Debbie Helsley
Share this vote →Aye · 8: Charles Thomas, Lynne Fugate, Debbie Helsley, Amelia Parker, Tommy Smith, Andrew Roberto, Lauren Rider, Gwen McKenzie
Absent · 1: Seema Singh