City of Knoxville · City Council
R-213-2012
Authorize change order for 2011 Resurfacing Project with Rogers Group.
Latest action, August 7, 2012: Adopted 7-0-1-1
1 meeting on record, oldest first.
-
Step 1
August 7, 2012A Resolution authorizing the Mayor to execute Change Order No. 1 to Contract No. C-12-0011 with Rogers Group, Inc., to increase the contract price by $358,534.71 for a new contract total of $6,659,903.23 for the 2011 Resurfacing Project, and extend the date of completion.(Requested by Department of Engineering)
Adopted 7-0-1-1Approve resolution
Moved by Finbarr Saunders · seconded by Duane Grieve
Share this vote →Aye · 7: Nick Pavlis, Duane Grieve, Brenda Palmer, Nick Della Volpe, Daniel T. Brown, George C. Wallace, Finbarr Saunders
Absent · 1: Mark Campen
Abstain · 1: Marshall Stair
Source: official minutes (PDF) for August 7, 2012, page 7.